October 8, 2026
On March 16, 2026, Healdsburg added Section 20.20.125 to its municipal code. Ordinance 1255 lets owners of single-family lots build a duplex or split the lot in two, and the units it creates fall outside the city's voter-approved growth cap. A second home you can sell is now possible on many lots in town. It comes with a city fee bill.
The gap between those two paths is set by one threshold in the city's fee schedule and one sentence in the new code. Anyone pricing a Healdsburg lot, as a buyer or a seller, is pricing which side of that gap the lot can reach.
Healdsburg voters approved Measure M on November 7, 2000. It limits residential building permits to an average of 30 a year and no more than 90 over three years. Affordable units and ADUs are exempt. Later measures added room for income-restricted multifamily housing, but the core ration on market-rate homes stayed in place.
The city's 2025 annual report shows how tight that ration has become. Of 121 residential permits issued in 2025, 116 were exempt from the cap: 106 affordable units, nine ADUs and one replacement unit. Only five Category A allocations went out that year. The city also reserved 45 Category B allocations for the Mill District through December 31, 2027. That leaves 15 for other projects of five or more units for the rest of the current cycle.
For an individual owner, that left two realistic ways to add a home. You could build an ADU, which is exempt but tied to the main house. Or you could compete for a handful of allocations. SB 9 now gives that owner a third path, and the city has written the cap out of it.
The exemption isn't a staff interpretation that could shift later. It's in the codified text:
"Because the City's Growth Management Ordinance is preempted by Government Code Sections 65852.21 or 66411.7, units developed under this section shall not be subject to the Growth Management Ordinance."
The Planning Commission stressed that exemption when it recommended adoption on January 27, 2026. The rest of the section sets the terms an owner works within. You can read them in full in Chapter 20.20 of the Healdsburg Municipal Code:
The right to sell a unit separately is the clause that matters most for pricing. The same section also attaches the full new-dwelling fee bill to every SB 9 unit.
Healdsburg's FY 2026-27 Master Fee Schedule took effect July 1, 2026. For a Tier 1 ADU of up to 850 square feet, it charges $0 in electric, fire, park, wastewater capacity and water capacity fees. The municipal code backs this up: ADUs up to 850 square feet are exempt from impact fees.
Tier 2 ADUs, between 851 and 1,200 square feet, pay a share of the single-family rate based on their size relative to the main house. That share is capped at 50%. If the ADU is built inside an existing house or accessory structure, it pays no water or wastewater capacity fees.
The cheap path stays attached to the main house, though. State law under AB 1033 lets cities allow ADUs to be sold separately, and Healdsburg staff reported that the city hasn't adopted a local process and that staff had received no inquiries. They described the steps it would require: a parcel or condominium map, recorded easements, separate utility meters, an HOA with CC&Rs, and lender consent if the property has a mortgage. In Healdsburg, an ADU adds rental income or family space. It doesn't create a second home you can sell.
Ordinance 1255 makes Two-Unit Developments "subject to all impact or development fees related to the development of a new dwelling unit." Each SB 9 unit also needs its own gas, electric and water connection to the utility. Lot splits pay the fees tied to creating a new parcel. At FY 2026-27 single-family rates, the city impact fees look like this:
| Fee line, single-family per dwelling unit | FY 2026-27 amount |
|---|---|
| Wastewater system capacity | $13,764.52 |
| Water system capacity | $8,299.16 |
| Storm drain facilities | $6,833.33 |
| Traffic facilities | $5,103.51 |
| Park system | $2,057.00 |
| Electric, up to 200 amp | $1,473.00 |
| Fire system | $193.00 |
| Total | $37,723.52 |
A lot split adds mapping costs. The SB 9 tentative map fee is $4,292.08 and the SB 9 final parcel map fee is $8,695.36, for $12,987.44 in maps before any surveyor's invoice. The separate connections carry their own line items. A water meter of 1 inch or smaller is $592.57 to install. A residential 200A time-of-use electric meter is $611.37. A single-phase 200A service panel runs $1,889.63 overhead or $3,457.56 underground.
Separate connections also mean separate recurring bills. Healdsburg's 2026 residential electric schedule charges each single-family account a $17.07 monthly customer charge. Water and wastewater rate increases of 13% and 15% were scheduled for FY 2026-27 under the package the council approved in 2024.
The Press Democrat and North Bay Business Journal reported that in Q2 2026, Healdsburg's median sale price was $1.33 million, up 9% from a year earlier, on 45 sales. Days on market rose to 43 from 34. Against home values at that level, roughly $38,000 in impact fees plus about $13,000 in map fees is a real cost. It is also a known, published cost, set by a ministerial process with a 60-day decision clock. Until March, a market-rate home outside the Measure M allocation process wasn't available to an individual owner at any price.
That moves part of a lot's value out of the existing house and into its geometry. Two lots with similar houses and similar list prices can carry very different options. One may divide into two parcels that each meet the 40% and 1,200-square-foot tests, with room for a 35-foot unit that respects the upper-story setback. The other may only fit an ADU. The first lot can produce a home that sells on its own. The second can produce rental income or space for family. Listing photos won't show the difference. A site plan and a fee estimate will.
There are three things to account for on the buy side. The three-year owner-occupancy affidavit applies to whoever files the split, so the plan has to fit how the buyer intends to live there. The ban on rentals under 30 days removes the vacation rental from the plan entirely. And because a split lot can't be split again, the first owner to use SB 9 on a parcel uses it up for every owner after.
For sellers, a lot with clean dimensions, existing utility access and a workable driveway has a feature that didn't exist in code a year ago. Driveways matter because all units must share a common driveway that meets Healdsburg Fire Department standards. Showing that feature with a basic feasibility sketch and a fee summary from the current schedule is far more useful than describing it as potential.
Two costs sit near this math, and neither is settled enough to include as a firm number.
No SB 9 applications in Healdsburg have been reported in city documents so far, so there is no local track record yet for timelines or approvals.
Does an SB 9 unit near the future SMART station need parking? The city report says the ordinance as proposed requires one parking space per unit, unless the parcel is within half a mile of a major transit stop such as a SMART rail station. The city is also starting a specific plan for the half-mile around the planned station and the South Entry Area. It is funded by a $1.13 million MTC grant and expected to take two to three years. Densities in that area may be revisited during that process.
Can a lot hold both an SB 9 unit and an ADU? On a lot that hasn't been split, the code allows a main house, an SB 9 unit and ADUs or JADUs, up to four units total. On each lot created by a split, the limit is two units in any combination.
Can an ADU in Healdsburg be sold separately today? No. The city hasn't adopted a local AB 1033 process, and staff weren't recommending one at the time of the February 2026 report.
Is this tax or legal advice? No. This post covers city code and the published fee schedule. A land-use attorney and a tax advisor should review any split or sale structure.
If you're weighing a Healdsburg lot for what Ordinance 1255 could let it become, Erik Terreri can run the site-fit and fee math alongside the market side before you set a price or write an offer. Contact Erik for a tailored market strategy and property consultation.
Whether buying or selling, trusted guidance ensures a seamless journey. Every detail is handled with care, turning real estate goals into achievements while providing clarity, confidence, and peace of mind throughout the process.